Day and Night Work Planned for Next Week - Oct. 13-17

Beginning Sunday, October 13 through Thursday, October 17, a night crew will work on utility patch paving. During night work, traffic on Pyramid Highway will be reduced to a single lane in each direction between Los Altos Parkway and Golden View Drive. Night work and lane reductions will occur between 8 p.m. and 7 a.m.


During the days, crews are continuing work north of Los Altos Parkway on installing curb, gutter and sidewalk, placing rock, drainage improvements, and constructing sound walls.


As always, please continue to use caution and slow down in the work zone. Our crews' lives depend on it.


The sound wall being installed on the west side of the highway is a post-and-panel wall. The technique uses prefabricated concrete panels and posts held together by drilled caissons. The largest panels are 18-feet-tall!