Paving Northbound Pyramid Highway Begins Sunday at 8 p.m.: Expect Nightly Lane Closures and Reductions

Milling, paving and striping of the northbound lanes of Pyramid Highway between Queen Way and Los Altos Parkway will begin this Sunday, April 28 at 8 p.m. and last through Friday, May 10. Crews will be working 24-hours-a-day, Sunday - Friday, with paving and traffic impacts occurring at night.


Drivers can expect the following:

  • Increased truck traffic through the work zone, please be patient and drive with caution

  • Traffic reduced to a single lane in each direction nightly: Northbound between 9 p.m. and 7 a.m., Southbound between 8 p.m. and 5 a.m.

  • Two lanes of traffic will remain open during the daytime hours


NDOT encourages you to continue to patronize area businesses during construction.


Drivers can also expect intermittent nighttime intersection closures at Disc Drive, Shoppers Way and Los Altos Parkway, with detours available.


Disc Drive Intersection Closure: 4/30, 5/2, 5/5 and 5/6
  • Closures of Disc Drive access to/from Pyramid Highway occurring at night from 8 p.m. to 7 a.m.

  • Traffic will detour to Los Altos Parkway to Sparks Boulevard to Disc Drive

  • Pyramid Highway reduced to single lanes in each direction

  • Shoppers Way access to/from Pyramid Highway also closed each of these nights


Los Altos Parkway Intersection Closure: 5/1 and 5/7
  • Closures of Los Altos Parkway access to/from Pyramid Highway occurring at night from 8 p.m. to 7 a.m. Walmart side beginning at 10 p.m.

  • Northbound traffic will detour Disc Drive to Sparks Boulevard to Pyramid Highway. Northbound traffic needing to access Walmart past 10 p.m. will need to enter from southbound Pyramid Highway via the northbound detour

  • Southbound traffic will detour Sparks Boulevard at the Pyramid Highway intersection to Disc Drive

  • Pyramid Highway reduced to single lanes in each direction

  • Shoppers Way access to/from Pyramid Highway intermittently closed

 

Pavement Striping

Crews will be striping and placing pavement paint from May 8 through May 10.


Pavement paint is quick drying, and will dry anywhere from one to five minutes depending on the temperature at the time of application. As a friendly reminder, try not drive over fresh paint when it is immediately placed to avoid paint splatter on your vehicle or smear marks on the pavement.


 