The first of two major construction weekends begins this Friday, October 13 at 9 p.m.

The first of two major construction "marathon" weekends will begin this Friday, October 13 at 9 p.m. Work will occur 24-hours-a-day until Monday, October 16 at 5 a.m. The second major construction weekend will take place beginning at 9 p.m. on Friday, October 20. These marathon weekends will allow crews to install necessary underground drainage across the highway as quickly as possible and help expedite the overall construction schedule.


October 13 at 9 p.m. to October 16 at 5 a.m.

Traffic and access changes during the day and night include:

  • One lane of traffic open in each direction on Pyramid

  • Speed reduced to 35 MPH

  • One through lane of traffic on Los Altos Pkwy (crossing Pyramid)

  • NO FREE RIGHT TURN from Los Altos Pkwy to northbound Pyramid

  • NO LEFT TURNS between Los Altos Pkwy and Golden View Dr

  • NO LEFT TURN from southbound Pyramid onto Los Altos Pkwy

All neighborhood accesses in the area will remain open with right-in and right-out only movements.


 

Milling & Paving Old Southbound Lanes Next Week: Queen Way to Los Altos Pkwy

Starting Monday, October 16 crews will begin milling, or grinding out, the old southbound lanes of Pyramid Highway between Queen Way and Los Altos Parkway and repaving them. Drivers can expect to see an increase in truck traffic in the area. Construction vehicles and trucks enter the work zone via southbound Pyramid near Los Altos Parkway, and they exit the work zone at the Farr Lane intersection.

Drive with caution and obey the speed limit while going through the work zone.

Once paving is complete, traffic will be shifted to the west side of the highway so widening operations can take place on the east side. The traffic shift is anticipated to happen the week of October 23.

Nightly Southbound Pyramid Closure During Paving

The southbound lanes on Pyramid Highway between Disc Drive and Farr Lane will be closed each night next week for paving operations. Nightly closures will occur between 9 p.m. and 4 a.m.

  • Southbound traffic will detour to Disc Drive to Sparks Boulevard, then to Baring Boulevard to McCarran Boulevard

  • Northbound Pyramid Highway will remain open but reduced to a single lane

 

NEARBY CONSTRUCTION ALERT:

I-80 and Pyramid Way Interchange Weekend Closures

NDOT will resurface the I-80 and Pyramid Way interchange in Sparks.

Drivers will see two weekend-long closures of the I-80 and Pyramid Way interchange beginning the evening of Oct. 20. Nearby detours will be available as the ramps are closed and resurfaced for a smoother and safer drive.